Already
funded or under construction
Exit
14 – complete in Fall 2018
Park
Street – under design, start construction in Spring 2019
Green
Springs Road – complete in October 2018
Abingdon
Urban Trail – complete in September 2018
VCT
@ Watauga Road - underway
Upcoming
East
Main Street sidewalks – FY2023
West
Main/Jonesboro Road intersection improvements – Design FY2021, Construction
FY2023
Additional
Maintenance Funds (Cummings Street, Porterfield Hwy, Jonesboro Road) – Fall
2018
West
Main/Porterfield Hwy intersection improvements – Design FY2020, Construction
FY2022-23
Exit
17 – FY2021
Exit
19 – FY2023
VCT
@ Meade Meadows – FY2019/20
Future
Applications
East
Main Street Widening from Exit 19 to Hillman Highway – Smart Scale
French
Moore Blvd. Extension – Smart Scale
Clark
Street Sidewalks - HSIP
Urban
Trail, Phase 2 – Transportation Alternative (TA)